Development

How Long Does A&A Work Usually Take?

Nov 2, 2025

-

Renee Ang

How Long Does A&A Work Usually Take?

If you’re planning A&A (Additions & Alterations) works for your landed home in Singapore, one of your biggest questions is probably:

“How long will the A&A process take from start to finish?”

Homeowners across Singapore, from terraces in Kovan, to semi-Ds in Sunset Way, to older bungalows in Namly, often underestimate how many stages are involved.

A&A work is faster than rebuilding, but still requires approvals, coordination, and sequencing.
This guide breaks down the full A&A timeline in simple, realistic phases, based on actual landed projects across Singapore.

1. Typical A&A Duration in Singapore (2026)

Total Timeline: 6 – 12 Months (On Average)

This includes:

  • design

  • submission

  • approvals

  • procurement

  • construction

  • inspections

  • handover

Actual duration depends on:

  • home age

  • structural complexity

  • size of extension

  • number of bathrooms added

  • neighbourhood access (affects speed)

  • engineer involvement

  • materials

  • monsoon season

2. Full A&A Timeline Breakdown

Below is a realistic, phase-by-phase guide used by contractors across Singapore.

**Phase 1: Design, Consultation & Site Study

(3 – 8 Weeks)**

What happens here:

  • homeowner shares requirements

  • architect surveys the house

  • structural engineer inspects existing beams & columns

  • feasibility checks for extensions

  • draft space planning

  • preliminary A&A concept is created

Why this phase matters:

Older houses in:

  • Frankel Estate

  • Serangoon Gardens

  • Seletar Hills

  • Hillview Gardens

  • Braddell Heights

  • Bedok South / Kew Drive
    often have unpredictable hidden conditions, meaning design must be carefully planned before approval.

Districts where design takes longer:

  • Joo Chiat / Mountbatten (heritage sensitivity)

  • Pasir Panjang slopes (terrain complexity)

  • Bukit Timah old bungalows (drainage & soil conditions)

For simpler terraces (e.g., Opera Estate, Kovan), design is faster.

**Phase 2: Authority Submissions

(4 – 12 Weeks)**

This is the phase most homeowners underestimate.
For any structural A&A work, the following approvals are required:

A. BCA Submission

Required for:

  • extensions

  • mezzanine

  • new openings

  • stair changes

  • roof works

  • structural reinforcement

B. URA Submission

Required for:

  • envelope control compliance

  • façade changes

  • attic changes

  • boundary setback adjustments

C. PUB Drainage & Sewer Submission

Especially important if adding bathrooms or extending the kitchen.

D. SCDF (if required)

Mostly for internal reconfiguration affecting escape paths.

Neighbourhoods where submission may take longer:

1. Terrace clusters with shared walls:

  • Opera Estate

  • Serangoon North

  • Lorong Ah Soo / Aster Estate

  • Sembawang Springs

  • Jalan Chempaka / Upper Changi

Neighbour protection works must be included in submissions.

2. Adjacent to conserved areas:

  • Joo Chiat

  • Emerald Hill fringe

  • Mountbatten

Elevational changes may require additional planning.

3. Sloped or hillside zones:

  • Pasir Panjang (Pepys Rd / South Buona Vista belt)

  • Hillview / Bukit Timah fringe

Slope stability affects engineering submissions.

**Phase 3: Pre-Construction (Procurement & Site Setup)

(2 – 6 Weeks)**

Activities include:

  • selecting tiles, fittings, windows

  • ordering carpentry materials

  • choosing roofing systems

  • preparing site hoarding

  • arranging skip bins

  • terminating/redistributing utilities

  • scheduling workers

  • scaffold installation

Neighbourhoods affecting this phase:

  • Narrow roads (Joo Chiat, Opera Estate, Thomson Ridge) slow down logistics.

  • Sloped roads (Pasir Panjang, Hillview) require safety planning for machinery.

  • Large bungalow plots (Namly, Watten, Brizay Park) require more setup time.

**Phase 4: Demolition & Structural Works

(3 – 10 Weeks)**

This is where real transformation begins.

Works include:

  • removing non-structural walls

  • breaking slabs (where approved)

  • opening new windows

  • demolishing old bathroom walls

  • roof partial demolition

  • internal reconfiguration

  • building new beams (if required)

  • constructing extensions

Factors affecting timeline:

  • thickness of old walls

  • strength of structural beams

  • unforeseen issues (spalling concrete, termite damage)

  • neighbour protection measures

Districts where structural phases may be slower:

  • Frankel Estate (older structural systems)

  • Serangoon Gardens (Mixture of 70s–90s houses)

  • Telok Kurau (old foundations, deep plots)

  • Hillview slopes (uneven soil profile)

  • Bukit Batok / Westwood landed pockets (older RC frame)

Older houses almost always reveal hidden surprises, extending structural works.

**Phase 5: M&E, Plumbing & Wiring

(4 – 8 Weeks)**

This phase covers:

  • full re-wiring

  • DB board upgrades

  • new plumbing runs

  • water heater installations

  • aircon trunking

  • ventilation ducts

Houses requiring longer M&E upgrades:

  • Thomson Ridge / Windsor Park (massive internal rewiring)

  • Seletar Hills (older copper piping systems)

  • Upper Changi & Bedok South (70s-era drainage layouts)

  • Pasir Panjang (complex aircon routing due to slope)

**Phase 6: Interior Construction, Carpentry & Finishing

(6 – 12 Weeks)**

Includes:

  • tiling

  • kitchen carpentry

  • wardrobes

  • feature walls

  • staircase finishing

  • glass installation

  • paint

  • fixtures & fittings

Districts influencing timeline:

  • Luxury bungalow zones (Namly, Watten, Holland), higher-spec material selections, custom carpentry → longer timeline.

  • Coastal areas (Siglap / Pasir Ris), waterproofing and salt-exposure considerations often take longer.

  • Terraces in constricted access zones (Opera Estate, Joo Chiat), material delivery slower, labour sequencing tighter.

**Phase 7: Final Inspection, Defects & Handover

(2 – 6 Weeks)**

Includes:

  • defects rectification

  • touch-ups

  • aircon testing

  • waterproofing verification

  • plumbing checks

  • BCA/URA completion checks (where required)

Factors affecting duration:

  • weather (monsoon season delays outdoor works)

  • custom carpentry defects

  • window alignment issues

  • waterproofing tests for new bathrooms

Estates where defects phase can stretch:

  • Older houses with uneven slabs causing tile alignment issues

  • Terraces with shared walls where neighbour-related issues arise

  • Houses on slopes where drainage must be tested thoroughly

3. What Affects A&A Duration Most? (Critical Factors)

1. Age of House

50-year-old structures in areas like:

  • Opera Estate

  • Serangoon Gardens (older units)

  • Thomson Garden Estate

  • Bedok South / Kembangan

  • Seletar Hills

… typically reveal issues that slow down progress.

2. Type of Extension Planned

Fast A&A:

  • internal reconfiguration

  • painting

  • carpentry upgrades

Moderate A&A:

  • rear extension

  • bathroom additions

Slow A&A:

  • attic enlargement

  • mezzanine construction

  • major façade redesign

3. Neighbour Protection Works (NPW)

Required for all terraces and many semi-Ds.
NPW adds time, especially in dense estates like:

  • Opera Estate

  • Serangoon North

  • Hougang landed pockets

  • Sembawang Springs

  • Compassvale Lane landed patch

4. Approval Complexity

Roof changes, façade transformations, and large extensions take longer to approve in:

  • conservation-adjacent zones

  • sloped districts

  • envelope control-sensitive areas like Watten, Namly, Brizay Park

5. Material Choice

Imported tiles, custom aluminium windows, bespoke carpentry extend timelines.

4. Fast vs Slow A&A Projects (Realistic Scenarios)

Fast A&A (6–7 Months):

  • small rear extension

  • kitchen + bathroom upgrade

  • minor façade work

  • internal wall reconfiguration
    Common in:

  • Kovan terraces

  • Serangoon North houses

  • Sunset Way semi-Ds

Moderate A&A (8–10 Months):

  • major kitchen & dining expansion

  • multiple new bathrooms

  • mezzanine addition

  • attic upgrades
    Common in:

  • Telok Kurau

  • Opera Estate

  • Seletar Hills

  • Bedok South landed zone

Complex A&A (11–12+ Months):

  • major façade transformation

  • roof redesign

  • multi-room extensions

  • extensive structural strengthening
    Common in:

  • Bukit Timah bungalows

  • Brizay Park

  • Holland / Coronation

  • larger Seletar or Springleaf detached houses

Useful Links

For homeowners planning an A&A project and needing timeline clarity:
🔗 A&A Contractor Singapore

If you're deciding between A&A speed vs rebuild duration:
🔗 Landed House Rebuild Contractor Singapore
🔗 Tear Down & Rebuild Singapore

For understanding what affects A&A timelines:
🔗 A&A Guidelines for Singapore Landed Homes, What BCA Allows & Doesn’t Allow

To prepare properly before starting A&A:
🔗 What to Prepare Before Starting A&A Works on Your Landed Home

For planning extensions and expansions:
🔗 How to Expand Your Landed Home Legally Using A&A Works
🔗 Tips to Maximise Floor Area Without Full Rebuild